First civil tender floated for construction of Phase I of Patna Metro Rail project

Anushka Khare Posted on: 2020-03-11 10:06:17 Viewer: 553 Comments: 0 Country: India City: Patna

First civil tender floated for construction of Phase I of Patna Metro Rail project

Patna, India (Urban Transport News): Delhi Metro Rail Corporation (DMRC) invites online bids from the experienced and eligible civil contractors for the construction of the viaduct, stations and depot for corridor I of Phase I of Patna Metro Rail project.

Scope of Work

Contract PC-01: Part Design and Construction of Elevated Viaduct, Viaduct connection to Depot including an elevated ramp for Depot, Stabling & Extension of Viaduct for Corridor-1 at Khemni Chak Station, Special Spans, Elevated Ramp at Malai Pakri and Five Elevated Stations viz. Malai Pakri, Khemni Chak (Interchange station), Bhoothnath, Zero Mile & New ISBT (Excluding Architectural Finishing works of stations & PEB works of stations) from Chainage 8020.000 mt. to 14127.726 mt. of Patna Railway station to New ISBT Corridor2 of Phase-I of Patna MRTS.

Important Information

  • NIT No.: PC-01/NIT
  • Issue Date: 29th February 2020
  • Estimated Value of Work: Rs 514.924 Crore
  • Earnest Money/Security Deposit: Rs 1.00 Crore
  • Work completion period: 30 months
  • Tender document cost: Rs 23,600.00
  • Availability of Tender Document: 29th February 2020 to 15th April 2020
  • Start date for submission of Bids: 8th April 2020
  • Last date for submission of Bids: 15th April 2020

Pre-bid Meeting and Contact Point

The pre-bid meeting is fixed on 18th March 2020 at the following address: Sr. General Manager/Contract Delhi Metro Rail Corporation, 5th Floor, A-Wing, Metro Bhawan, Fire Brigade Lane, Barakhamba Road, New Delhi –110001

Project details

  • Delhi Metro Rail Corporation (DMRC) is appointed as a General Consultant for the execution of phase I of the Patna Metro Rail project.
  • AECOM is appointed as Detailed Designed Consultant for Civil work of the project.
  • SYSTRA MVA appointed as Detailed Designed Consultant for Traction and SCADA work of the project.




Also Read