DMRC floats first Underground tender for Delhi Metro Phase IV

Anushka Khare Posted on: 2019-10-03 08:44:39 Viewer: 626 Comments: 0 Country: India City: Delhi

DMRC floats first Underground tender for Delhi Metro Phase IV

New Delhi (Urban Transport News): Bids invited from the eligible firms through the international competitive bidding (ICB) process for the design and construction of the underground tunnel under Delhi Metro Phase-IV corridors.

Scope of Work

Design and Construction of Twin Tunnel by Shield TBM, Cut & Cover Tunnel box, Underground ramp and one Underground station namely Krishna Park Extn. with Entry/Exit & Connecting subway by Box pushing method including Architectural Finishing, Water Supply, Sanitary Installation & Drainage works from chainage 805.110mt. to 2830.863mt. (UP Line) & from chainage 788.198 mt. to 2814.745 mt. (DN Line) of Janakpuri West to RK Ashram Corridor (Extension of Line 8) of Delhi Metro Phase IV.

Key Information

  • Approximate cost of work: INR 478.12 crores
  • Tender Security amount: INR 478.12 Lakh
  • The completion period of the Work: 36 months
  • Tender documents on sale: From 03.10.2019 to 13.11.2019
  • Cost of Tender documents: Rs 23600.00 (including 18% GST)
  • Pre-bid Meeting: 15.10.2019
  • Tender submission start date: 06.11.2019
  • Tender submission end date: 13.11.2019
  • Date & time of opening of Tender (Online): 14.11.2019

Minimum Eligibility Criteria

Work Experience

At least one similar work of value of Rs.382.50 crore or two similar works each of the value of Rs. 239.06 crore or three similar works each of value of Rs. 191.25 crore or more.

Financial Standing

  • Liquidity: Bidder should meet the cash flow of Rs 22.77 crores for this contract.
  • Profitability: Profit before Tax should be Positive in at least two financial years, out of the last five audited years.
  • Net Worth: Net Worth of tenderer during the last audited financial year should be >Rs. 31.87 crore.
  • Annual Turnover: The average annual turnover from the construction of the last five financial years should be > Rs. 127.50 crore.

Contact Point

Authority for the purchase of tender documents, seeking clarifications and submission of completed tender documents and place to attend the Pre-bid meeting: – Chief General Manager/Contracts, Delhi Metro Rail Corporation, 5th Floor, A-Wing, Metro Bhawan, Fire Brigade Lane, Barakhamba Road, New Delhi –110001