Govt of India approves Integrated Transport & Logistics Authority to drive Multimodal Planning
PCMC approves ₹85 Lakh for DPR of Maharashtra’s First e-RTS Pilot Corridor
Visakhapatnam partners with Moscow to build Technology-Driven Urban Transport System
Biofuels in Shipping: A Transitional Solution or Long-Term Strategy?
8 Reasons Why Trains Are Still One of the Best Ways to Travel
Interview with Champak Panda, MD-Rolling Stock & Components, Alstom India
Beyond the Tailpipe: The Case for African Electric Mass Transit
A Rejected Claim Is Not Always the End, What Car Owners Can Do Next?
Monsoon Bike Insurance Guide: Covers That Matter before the Rains Begin
How Train Transportation Creates Faster and Smarter Cities
Chennai, India (Urban Transport News): The Chennai Metro Rail Limited (CMRL) awarded a contract order worth Rs 187.48 crores to the consortium of Altis Holding Corporation (AHC) and Varindera Constructions Limited (VCL) for the construction of Poonamallee Depot for Corridor 4 of Chennai Metro Rail Project, Phase 2.
The scope of work includes construction of metro depot at Poonamallee including Structural Works, Architectural Finishes, Plumbing Works, Signages, Utility shifting & Boundary wall and all Associated works for corridor 4 of Chennai Metro Rail project.
Tender for the contract package DPT-01 was floated in January this year and technical bids were opened in July. Financial bides were opened in Spetember and AHC-VCL JV was declared as lowest bidder (L1) for this contract package. A total of five bidders were submitted their bids whose finacial positions are as under:
Now the AHC-VCL JV has to complete the construction of Poonamallee depot in three years from the date of issuance of LoA. The depot will be built in 17 hectares area of land and will have a facility for 24 tracks that can fit six coach trains. Apart from this, staff accomodation will also be constructed in this depot.
According to CMRL officials, the first stretch between Poonamallee and Power House is an elevated stretch and will be constructed initially within four years. There are only two depots, with the biggest one at Madhavaram and the other at Poonamallee.
For more details, please explore our Chennai Metro page of Urban Transport News.