Maha Metro launches tender for procurement of Rolling Stock for Nashik Metro Neo project

Anushka Khare Posted on: 2021-03-27 09:15:00 Viewer: 5,543 Comments: 0 Country: India City: Nashik

Maha Metro launches tender for procurement of Rolling Stock for Nashik Metro Neo project

Nashik, India (Urban Transport News): The Maharashtra Metro Rail Corporation Ltd (Maha Metro) on 22nd March 2021 invites Expressions of Interest (EOI) for providing 50 Coaches (36 coaches for corridor 1 and 14 coaches for corridor 2) for India's first proposed Metro Neo project in Nashik.

The Expression of Interest (EOI) published by Maha Metro is aimed to solicit and examine the response of the firms/companies/entities that are supplying or capable of supplying the Trolley Buses and their maintenance for the Metro Neo project.

Key information

  • EOI Notice No.: NS1-RS-02/2021
  • Documents on sale: 23.03.2021 to 05.05.2021 up to 16.00 hrs.
  • Work Completion Period: 18 months
  • Date & Time of Pre-EOI Meeting: 20.04.2021 at 11.00 hrs
  • Meeting Venue: METRO BHAVAN, East High Court Raod (VIP Road),Opp Dr.Babasaheb Ambedkar College, Near Diksha Bhoomi, Nagpur – 440010, Maharashtra, India
  • Date & Time of submission of EOIs: 05.05.2021 up to 16.00 hrs. through Maha Metro’s e-tender portal
  • Date & Time of Opening of EOIs: 05.05.2021 at 16.30 hrs.

The Metro Neo system is to be implemented in tier 2 or tier 3 Indian cities with over 8000PHPDT where the heavy metro is not viable. This document describes few technical requirements for such a system named Metro Neo which will be at a much lesser cost, rail-guided, rubber tyred electric coaches powered by overhead traction system running on a road slab (elevated/at-grade). 

'MetroNeo' would also act as a feeder system to high capacity Metro in Tier 1 metropolitan cities and shall act as the main transport system in tier 2 or tier 3 Indian cities. In addition to less capital cost, the operation and maintenance cost of Metro neo would also be less making the system more viable. The proposed model envisages seeking offers from applicants for design, manufacture, supply, testing, commissioning of the tyred based electric bus running on the overhead equipment (OHE) and training of personnel (Metro Neo in Nashik) of Maharashtra Metro Rail Corporation Ltd.

The criteria for the availability of Trolley Buses shall be detailed in the RFP document. The Contractor shall be responsible for design, manufacture, supply, testing, commissioning of tyred based electric bus running on OHE and training of personnel as per the contract. 

Corridor 1: The 22 km route will connect Gangapur to Nashik Road Railway Station with 20 elevated/at grade stations.

Corridor 2: The 10 km route will connect Gangapur to Mumbai Naka with 10 elevated/at grade stations.

The estimated cost of the Nashik Metro Neo project is Rs 2,092 crores.