Chennai Metro to appoint General Consultants for Corridor 4

Anushka Khare Posted on: 2021-06-04 07:40:00 Viewer: 6,040 Comments: 0 Country: India City: Chennai

Chennai Metro to appoint General Consultants for Corridor 4

Chennai, India (Urban Transport News): After cancelling the previous bidding process, Chennai Metro Rail Limited (CMRL) has issued a new tender notice for the selection of General Consultants for 26.01 km Corridor 4 (Light House - Poonamallee) of Phase 2 of Chennai Metro Rail Project.

"Due to administrative reasons, the current RFP for Selection of General Consultant (GC) for Chennai Metro Rail Phase 2 Project – Corridor 4 is cancelled," said an official release issued by CMRL. However, sources said that some of the participants were not happy with the parameters and methods being used by CMRL during the evaluation of bids. Hence, the tendering process cancelled before the opening of financial bids.

Scope of Work

Selection of General Consultant (GC) for Chennai Metro Rail Phase 2 Project – Corridor 4 and part of Corridor-3 & 5.

Key Information

  • Tender Notice No. CMRL-P2-GC-02-2021
  • Issue Date: June 2, 2021
  • Work Completion Period: 63 months
  • Pre-bid Meeting: 16.06.2021 at 15.00 hrs.
  • Last Date for Submission of Bids: 14.07.2021 till 18.00 hrs.
  • Opening Date of Technical Bids: 15.072021 at 10.00 hrs.

In January 2020, CMRL had invited Expression of Interests (EOIs) for the selection of General Consultants to provide General Consultancy Services to assist CMRL in the preparation and implementation of Corridor 4 of Phase II of the Chennai Metro Rail Project. A total of 9 proposals received in June 2020. A total of 7 consortia shortlisted to submit their bids in August 2020. Out of four consortia disqualified during the technical evaluation stage and finally three consortia (JV of AECOM Asia Company Ltd., SYSTRA and Consulting Engineers Group (CEG) Ltd.; JV of Egis Rail SA, MM SPA, Italferr SPA and Surbano Jurong Infrastructure Pte Ltd and JV of Louis Berger SAS, Geodata Engineering SpA and Hill International Inc.) have been shortlisted in February 2021.

Corridor 4 of Phase 2 of the Chennai Metro Rail project will connect Lighthouse with Poonamallee Bypass via Porur through 28 stations – 18 elevated and 10 underground.

In 2019, a consortium of Nippon Koei – Aarvee Associates – Balaji Railroads Systems was appointed as General Consultant for Corridor 3 & Corridor 5 of Phase 2 of the Chennai Metro Rail project.